Status date 15 Sep 2026Overall AmberForecast finish 14 Nov 2027vs 30 Oct 2027 commitment +15 daysIllustrative data
Portfolio — all locations
India-wide view across every project in the portfolio — industrial, commercial, healthcare, infrastructure and data centre. Pune and Hyderabad are live on the Control Tower today; the remaining locations are shown as pipeline projects with illustrative figures, pending confirmation of scope and timing.
India — All Project Locations
Progress by Location — Actual vs Plan (%)
Location Detail
Actions needed
Major delays
What’s going right
What’s going wrong
Pune & Hyderabad — Site Locations
Overall S-Curve — Baseline vs Planned vs Actual
Status at a Glance — Every Dimension in One View
Milestone Scoreboard — Next 4
Milestone
Baseline
Forecast
Status
AmberForecast finish 14 Nov 2027 — 15 working days past the 30 Oct 2027 commitment
Work done 32.4% against 41.8% planned by now. The delay is driven by a design revision hold on Zone A (Pune) and long-lead chiller package delivery slipping to Dec 2026. Civil works at Pune are 46 days behind baseline due to monsoon impact and late piling start. Environmental Clearance / Consent to Establish (SPCB) is on the critical path.
14 Nov '27
Forecast Finish
+15d vs commitment
32.4%
Work Done vs Planned
Plan: 41.8% · Behind plan
4 / 14
Milestones Met
3 at risk · 7 upcoming
7
Open Constraints
2 critical · 3 high
₹950 Cr+
Combined CapEx
Pune + Hyderabad · Phase 1
Forecast Finish Trend — Monthly Schedule Reviews
Each point is that month's re-forecast of the finish date, shown as days early/late vs the 30 Oct 2027 committed date (dashed line = 0 = on time). Feb–May'26: slippage grew as design revision holds cascaded. Jun'26: a recovery plan (resequenced civil works) briefly closed the gap. Jul'26 onward: new risks (SPCB clearance, procurement delays) pushed the forecast out again to the current +15d.
Work Done vs Planned — % of Project
Driving the Delay
Primary delay driver
Design Revision Hold — Zone A
Rev 3 not issued. Foundation design cannot be finalised. 14 activities on hold. Civil works cascade delay: ~3 weeks.
CRITICAL Owner: Client / Design Consultant Overdue: 16 days
Sets the end date
Environmental Clearance / CTE (SPCB)
Consent to Establish pending with the State Pollution Control Board. Construction halt risk if not received by Oct 2026. Currently on critical path.
HIGH Owner: Client — Approvals Target: 30 Sep 2026
Procurement risk
Chiller Package Delivery — Dec 2026
Long-lead plant delayed by 8 weeks. Zone B installation sequence blocked until the chillers land on site.
HIGH Owner: PMC Procurement Impact: Zone B start
What Changed — Last 2 Weeks (1 Sep → 15 Sep 2026)
Milestone Movements — 5 biggest slips
Milestone
Group
Was
Now
Slip
Complete Foundations — Pune Zone A
Construction Milestones
15 Aug 2026
30 Sep 2026
+46d late
Environmental Clearance / CTE (SPCB)
Regulatory Milestones
01 Sep 2026
31 Oct 2026
+60d late
Major PO Placement (>80% value)
Procurement Milestones
31 May 2026
30 Jun 2026
+30d late
Design Freeze — Zones A & B
Design Milestones
30 Apr 2026
15 May 2026
+15d late
Equipment Installation Start — Pune
Construction Milestones
15 Nov 2026
15 Jan 2027
+61d late
14 Nov 2027
Forecast Finish
+15 days vs 30 Oct commitment
4 / 14
Milestones Met
3 At Risk · 7 Not Started
32.4%
Overall Progress
Plan: 41.8%
30 Oct 2027
Committed Deadline
Fixed — Client requirement
Overall S-Curve — Baseline vs Planned vs Actual vs Forecast
Site photos
RAG Zone — Schedule Variance by Discipline
Site Photos — Placed Directly in Dashboard by PMO
Close
Sample only — in production, the PMO uploads site photos directly into this dashboard each reporting cycle (weekly, monthly, or as agreed). No separate PPT step required.
Milestone Scoreboard
ID
Milestone
Baseline
Forecast
Variance (days)
Status
Weekly Quantity-Based Tracking — Scope vs Planned vs Actual vs Balance
Quantities tracked at activity level — each row shows total scope, planned cumulative, actual achieved, and balance remaining. Updated weekly by VisiLean PMO from site DPRs. RAG auto-computed against planned-till-date: Green only if actual is at/above plan · up to 5% behind = Amber · more than 5% behind = Red. (Unlike schedule-variance RAG elsewhere, any quantity shortfall is never Green.)
Quantity Tracker — All Sites
Site
Area
Discipline
UoM
Scope
Planned Qty (till date)
Actual Qty
Balance
Planned till date %
Actual %
Variance
Skilled
Unskilled
RAG
Weekly Liquidation Profile — Planned vs Actual per Discipline
Each chart shows weekly planned increment and actual progress for a discipline. Cumulative S-curve overlaid. Data updated every Monday from previous week's DPRs. Missing bars indicate weeks with no data yet submitted.
Weekly Liquidation — Civil
All Disciplines — Cumulative Progress %
Recovery Required — Portfolio S-Curve
What It Takes To Still Hit 30 Oct 2027
The bold red line below is the run-rate the whole programme needs to hold from now on to close the gap to the committed date — not a system forecast, but the plan VisiLean's planners build by hand: re-sequencing activities and resetting quantity assumptions week by week in the New Table View until the curve closes. VisiLean does not auto-level resources against the plan; this line moves only when a planner moves it.
Cumulative % Complete — Actual vs Recovery Rate Required
Weekly Summary Table — All Disciplines
Discipline
Total Scope
Planned This Week
Actual This Week
Variance
Cum Planned %
Cum Actual %
Cum Variance
Rate Needed to Recover
RAG
Productivity-Based Planning — Run Rate vs Required Rate
Since all contracts are unit-rate (no resource-loaded schedules), productivity is computed from: Actual Qty completed ÷ Workers deployed = daily run rate. Asking Rate = remaining scope ÷ remaining calendar days. Red = asking rate >2× actual rate.
Run Rate vs Planned Rate vs Asking Rate (% scope/week)
Workers on Site — Daily Average by Discipline
Are We Building Fast Enough?
Phase / Discipline
Done
Plan (till date)
Done/Plan
Actual Rate (last 4 wks)
Planned Rate
Asking Rate
Workers (avg)
Step-up Needed
RAG
Design Deliverables Tracker — Key Deliverables Only
Tracked at deliverable type level (not individual drawing numbers). Stages: Not Started → IFA (Issued for Approval) → Client Comments → IFC (Issued for Construction) → Approved. Each deliverable type tracked against baseline and forecast completion.
10
Deliverable Types Tracked
72.4%
Overall Design % Done
Plan: 85.2%
28
Open Design Review Actions
Blocking IFC for Zone C
3
Deliverables On Hold
Design Progress by Deliverable Type
IFA vs IFC vs Approved — Count by Type
Design Deliverables Register — Planned-till-date vs Actual, Gap Visible
Deliverable Type
Total Docs
Issued (IFA)
Approved (IFC)
On Hold
Planned Qty (till date)
Actual Qty / %
Gap
Baseline
Forecast
Status
Knock-on Effect — Delay Propagation Across Dependent Deliverables
Deliverables are logically dependent — a delay upstream (e.g. concept design not yet frozen) puts every downstream deliverable that relies on it at risk, even where the downstream team has continued drafting on a preliminary basis.
Deep-Dive Construction Tracker — WBS/Activity-Level Progress, Delay Q&A
Civil and structural construction activities tracked at WBS/activity level with baseline vs forecast completion. Where an activity is delayed, the planner logs the delay reason, the responsible party, and the expected resolution — this view drives the weekly review meeting.
Activity Gantt — Baseline vs Forecast
Constraint / Delay Log — Planner Q&A
WBS / Activity
Site
Discipline
Baseline Finish
Forecast Finish
% Complete
Delay
Delay Reason
Responsible Party
Expected Resolution
Status
Procurement Tagged Item Tracker — PO Placed → Lead Period → Material Delivered → Erected
Each equipment category tracked through 4 lifecycle stages, quantity-first: count of tags reached vs the count that should have been reached by now (Planned-till-date), so the gap — and therefore the RAG — is self-explanatory. Modelled on LLE (Long Lead Equipment) methodology.
Constraints & Action Register — Daily DPR Actions + Weekly Review Actions
Actions arising from DPRs and meetings are logged here with owner, target date, and linked activities. MoM documentation is managed by the PMC externally; action closure status is updated in VisiLean weekly.
7
Total Open Constraints
2
Critical
3
High
1
Committed
Constraints by Category
Action Closure Trend
Open Constraints — Priority List
#
ID
Type
Constraint Title
Area
Raised
Target
Holds / Impact
Owner
Status
Priority
Work Fronts — Phase Status & Rate Needed to Recover
Each construction phase on its own terms: how much of the project it carries, how much is built, what is running, and the rate needed to recover the committed finish date.