Anonymised sample — ROB, HPC and Interchange are left out of every totalAbout this data
Client, project name, location and original chainages have been removed. Chainage is measured from a notional project start (Km 0), and subcontractors are labelled A–I. Quantities, counts, statuses and variances are unchanged from the source. No cost data is shown; dates and variance are at structure-type level. ROB, HPC and Interchange are excluded because no verifiable count exists for them.
Schedule
Quantities
Chainage-wise progress
Km 0 to 28.8 · 136 of 176 structures have a recorded chainage
Weighted progress by 4 km section
Physical progress by structure type
Weighted progress = completed + ½ in progress, over actual site count
Planned vs actual count
BOQ against structures found on site
BOQ plannedActual on site
Schedule variance by type
Days late, actual end against baseline
Anonymised sample for illustration. Subcontractors A–I are placeholders.