VisiLean · Highway structures

Schedule G — structures progress

~28 km national highway package · structure DPR, Sep 2026, against the construction programme baseline
Anonymised sample — ROB, HPC and Interchange are left out of every totalAbout this data

Client, project name, location and original chainages have been removed. Chainage is measured from a notional project start (Km 0), and subcontractors are labelled A–I. Quantities, counts, statuses and variances are unchanged from the source. No cost data is shown; dates and variance are at structure-type level. ROB, HPC and Interchange are excluded because no verifiable count exists for them.

Schedule
Quantities

Chainage-wise progress

Km 0 to 28.8 · 136 of 176 structures have a recorded chainage

Weighted progress by 4 km section

Physical progress by structure type

Weighted progress = completed + ½ in progress, over actual site count

Planned vs actual count

BOQ against structures found on site

BOQ plannedActual on site

Schedule variance by type

Days late, actual end against baseline

Anonymised sample for illustration. Subcontractors A–I are placeholders.